1. Before installation

  • Confirm the position is shadow-free — nothing above the panel (trees, buildings) at any time of day.
  • Tools: shovels, spirit level, wrenches, multimeter, harness for work at height.
  • Check the kit: pole, lamp head, panel, battery, controller, anchor bolts — all present and matching the configuration sheet.

2. Foundation (the step that decides everything)

  • Excavation sizes: 6 m pole 600×600×800 mm; 8 m pole 700×700×1000 mm; 10 m pole 800×800×1200 mm. Increase by 20–30% in backfill, soft or frozen soil.
  • Set the anchor-bolt cage (6 m poles: 4×M20; 8 m and above: 4×M24). Tape the threaded ends to keep concrete off, and level all four bolt tops with a spirit level.
  • Pour C25 concrete and cure 3–5 days before erecting the pole.

A weak foundation is the main cause of fallen poles. Pour it solid, and never erect the pole inside the curing window.

3. Assembly and wiring

  • Place the battery into the pole's battery box or internal compartment.
  • Wire in controller order: battery → lamp head → panel. Never reverse polarity.
  • Verify voltages with the multimeter, then tighten all terminals.

Note: connect battery first, then lamp head, panel last. Disassembly is the reverse — disconnect the panel first.

4. Erection and commissioning

  • Lift the pole with a crane or tripod and align it over the anchor bolts.
  • Tighten the nuts and check verticality with a spirit level.
  • Cover the panel to simulate nightfall and confirm the lamp switches on automatically.
  • Set the lighting profile — typically full output in the first half of the night, half power after.

Choosing the fixing method

MethodSiteNotes
Cast concrete foundationShoulders, green belts, rural roadsExcavate → set anchor cage → C25 → cure. Most common; no erection during curing.
Direct burialDense soil, short stretches, tight budgetsBury pole base 800–1000 mm with compacted gravel backfill. Weaker against wind; not recommended above 8 m.
Chemical / expansion anchorsConcrete roads, bridges, hard surfacesDrill → clean → anchor → bolt the flange. Avoid rebar; hole depth follows anchor spec.
Bracket / wall mountWalls, existing utility polesClamp or bracket plus anti-drop cable. Check wall strength against lamp weight first.

In frozen or backfilled ground the foundation must sit below the frost line, or the pole tilts when the ground thaws in spring.

Crew and equipment planning

Pole heightCrewEquipmentTime per set*
4–6 m2–3 peopleUsually none needed40–60 min
8 m3–4 peopleTriad or small crane advised1–1.5 h
10–12 m4 + 1 signalmanCrane required1.5–2 h

*Excluding foundation works, which must be scheduled separately. At this pace a 2-person crew installs 5–8 six-metre sets per day; a 100-set village-road project realistically takes 15–20 days including foundations and curing. To compress the schedule, stage the work: pour all foundations first, assemble poles during curing, then lift them all.

What the installation fee should include

Reconcile this list before signing, to avoid surprises later: excavation and backfill, concrete and rebar, anchor cage setting and levelling, pole assembly and internal wiring, lifting and erection, lamp and panel mounting, controller commissioning, transport (extra-long sections charged per metre) and re-handling, work-at-height measures and crane shifts. Usually excluded: pavement cutting and reinstatement, green-belt relocation, cable trenching (grid models), grid-connection procedures. If the site needs them, say so up front.

After installation, if a light does not come on, follow the commissioning checks above — panel cover test, polarity, terminal torque — before assuming a fault. For a matching configuration, see the solar street light page or send us your site details.